環海翡翠輪完成海龍二號風場水下基礎及海上變電站安裝作業

CDWE concludes Hai Long 2 Offshore Wind Project Foundation & Offshore Substation installation in Taiwan. 

We’re proud to share the completion of the first offshore installation campaign for the Hai Long Offshore Wind Project! Leveraging our DP3 heavy lift vessel GreenJade, CDWE has installed all jacket foundations and the offshore substation (OSS) at Hai Long 2 and the foundation of the Hai Long 3 OSS. The Hai Long Offshore Wind Project held a blessing ceremony in April this year, officially announcing the launch of offshore construction. 

Working in challenging water depths between 35-55m and distances of 45-55km offshore, Green Jade has impressively installed:
ž 111 pin piles
 37 jacket foundations
 2 OSS jacket foundations
 1 OSS topside 
 
These accomplishments cover a significant part of the 73 turbine locations for the Hai Long Offshore Wind Project. 

A huge thank you to the Client Hai Long Offshore Wind Project team, our CDWE team members and our (local) partners and suppliers who made this achievement possible! Proud to have contributed continuously in delivering clean, renewable energy to Taiwan!