CDWE is proud to mark a major milestone with the successful installation of the first wind turbine for the Hai Long 3 project—officially launching our 2026 WTG installation campaign.
This campaign represents the major piece of the puzzle in the more than 1GW Hai Long wind farm installation works, moving steadily toward full grid connection.
CDWE has achieved the following key milestones since 2024, including:
• 219 pin piles installed
• 73 jacket foundations installed
• 2 offshore substations completed
• 37 wind turbines installed
We are honored to contribute to building one of Taiwan’s largest offshore wind farms and proud of the progress achieved together.
A sincere thank you to our CDWE project teams onshore and offshore, as well as the crew onboard the jack-up turbine installation vessel Sea Challenger, for their dedication and relentless efforts on this campaign.